Related links
Facts and figures
All figures in a row , since the start Gate terminal in 2008 to its completion in 2011.
Location
Where: Northern part of the existing Maasvlakte in the Port of RotterdamContract: Long-term 50-year leaseArea: 35 hectares
Terminal
- Total maximum throughput capacity: 16 bcm per annum, planned start-up capacity: 12 bcm per annum
- Net capacity of tanks: 180,000 cum per tank, total capacity 540,000 cum
- Gross capacity of tanks: 200,000 cum per tank
- Dimensions of tanks: 55 metres in the centre to top of dome roof / diameter about 86 metres,
- Type of tank: Full containment: steel inner tank, thermal insulation and concrete outer tank
- Initial capacity: 12 bcm p.a., realised by building 3 storage tanks and 2 jetty’s
- Expansion: At 12 bcm p.a. a second jetty, at 16 bcm p.a. a fourth tank
- Vessel discharge rate: 12.500 m3/hr LNG
- Vessels: All standard LNG carriers
- Expected number of ship movements: 180 per annum (based on throughput of 8 – 12 bcm)
- Operational: September 2011
Contracts
Customers: DONG Energy, RWE Supply & Trading, EconGas OMV, E.ON Ruhrgas, Eneco.
Contracted throughput capacity: In total 12 bcma/yr
EPC contractor: Consortium van Techint, Sener, Entrepose and Vinci
Costs
Project costs: Estimated at EUR 800 million
Project milestones
- August 2005: feasibility study
- November 2005: licensing procedure started
- November 2005: start of open season for terminal capacity
- November 2006: environmental permit granted
- April 2007: 20-year exemption from Gas Act for 16 bcm/per annum
- April 2007: lease agreement with port authority (finalized in October)
- July 2007: EPC contract, with commencement preparations
- August 2007: Site reclamation completed by Port Authority of Rotterdam
- 17 December 2007: contracts with Dong, Econgas, Essent
- 28 June 2008: Official start of the construction by Maria van der Hoeven, Minister of Economic Affairs
- 21 July 2008: signing of EUR 745 senior project financing with European Investment Bank an a syndicate of 10 relationship banks
- 4 August 2008: contract with E.ON Ruhrgas
- 18 March 2009: expansion project financing agreement of EUR 136 million
- 8 July 2009: Gate terminal reaches highest point in the building process >
- 18 March 2010: Iberdrola to deliver LNG to DONG Energy from 2011
- 2 June 2010: 2 million man-hours without LTI at Gate terminal
- 2 June 2010: Gate terminal invests to further increase its flexibility of LNG supply
- 22 December 2010: Eneco and Gate terminal sign multi-year agreement
- 3 June 2011: Gate terminal starts with commissioning phase LNG terminal
- 5 July 2011: One of the world’s largest LNG carrier’s the Q-Max ‘Al Samriya’ arrives at Gate terminal
- 27 July 2011: LNG carrier Arctic Voyager docks at Gate terminal
- 1 September 2011: First commercial LNG cargo arrives at Gate terminal
- 23 September 2011: Her Majesty Queen Beatrix of the Netherlands officially opens first Dutch Liquefied Natural Gas Import Terminal
Next steps
- Site preparation tanks & process area (first half 2008)
- Installation of site accommodation & temporary facilities (2008)
- Construction of LNG outer tanks (2008 – 2009)
- Construction of LNG inner tanks (2009 – 2010)
- Construction of jetty substructure (2009)
- Construction of jetty topside (2010)
- Construction of process area with piping and equipment to vaporise LNG (2009 – 2010)
- Connections to hot water, electricity and natural gas transport pipeline (2009-2010)
- Mechanical completion of the construction work and pre-commissioning activities
- Introduction of first liquid natural gas to cool and test the plant (first half 2011)
- Final commissioning for commercial operations (September 2011)
Employment
During construction: average 400 to 600 people for three years on site and similar numbers indirectly at suppliers. When the terminal is in operation: circa 35 personnel directly at the location.


